ThistlePro® FastSet Finish Installation Instructions

The guidance below shows how to apply ThistlePro® FastSet Finish plaster – All times stated are approximate.

The guaranteed way to get the job done faster.

Installation Guidance

0 mins

  • Add approx 11.5 litres of clean water per 25kg bag to mixing bucket. Gradually add the plaster to water whilst mixing.
  • Complete 1st coat (1mm thick)

10 -15 mins

  • Complete 2nd coat (1mm thick), the total thickness for both coats should be a minimum of 2mm

15 - 25 mins

  • Closing in

35 mins

  • 1st trowel

45 mins

  • 2nd trowel

70 mins

  • Final trowel to a flat, matt finish (Lubricated with minimal water)

Times and processes are given as guidance. On site practice may vary. Finishing times are reduced by suction and extended by cold weather conditions.

NOTE: For ThistlePro® FastSet Finish, we recommend a single mix for both first and second coat. Ensure that the product is suitable for the background to which it is being applied by using the Plaster Selector Guide.