The Lowry Centre

Salford Quays

The Lowry Centre

Main Focus

The main focus The main focus of the project was installation of a unique suspended ceiling in the foyer of the 1,730 seat Lyric Theatre situated within the Lowry Centre. This new national venue for the performing arts is one of the early Best Practice demonstration projects following Egans Rethinking Construction.

Challenge

The challenge The challenge demanded a suspended ceiling profile that had never been attempted before. The ceiling was required to span approximately 9 metres, sloping from one side down to the other. The surface at the top end was to be flat and gradually transform into a pronounced wavy surface at the lower end. The problem was compounded because both adjoining walls were either curved on plan, or at an unusual angle to the proposed ceiling. This complicated aesthetic design also had to provide 60 minutes fire resistance from below.

Solution

The solution The solution was to fit Gypframe 146 I 90 'I' Studs, from a fixed point and then twist along the run of the slope to achieve the correct profile. This framework was then lined with multiple layers of 6mm Glasroc MultiBoard, with 150mm rock mineral wool to complete the system. A full scale mock up was successfully erected at the Building Test Centre to prove the principle to subcontractors and architects. This solution eliminated the need for complicated computer-aided design, facilitating simpler on-site installation and a reduction in the amount of hangers required.

Main Contractor: Bovis
Subcontractor: Horbury Building Systems Ltd
Architect: Michael Wilford & Partners

Back to Showcase Selector

Back to Showcase Selector

The Lowry Centre

Products featured

GypWall Metal Stud

Glasroc MultiBoard

 Fire  1 hour
   
   

 

The Lowry Centre